Hixtra · site concrete testing
Concrete testing. On your site.
Fresh concrete testing, sampling and specimen preparation, coordinated around your pour schedule and specification. Here is what we cover on site and how to arrange it.
Talk to Hixtra →01908 505833Same-day & next-day testing dates available. Call to check availability for your location and test requirements. Fresh concrete testing coordinated with the planned pour.

Quality, safety & professional standards
Expertise you can check.
UKAS accreditation applies to the tests listed in our accredited schedule. Ask us for the current scope before you book.
Understand our accreditation →



Coordinated with your pour
Sampling and testing arranged around the planned pour schedule.
Experienced people
Correctly maintained equipment and consistent site practice.
National coverage
Same-day and next-day testing dates available across England and Wales.
Questions people ask
Your questions, answered.
Practical answers for planning and booking on-site concrete testing.
Ask us about your project →Should we book slump or flow testing?
It depends on the concrete specification and the workability class specified. Send the specification and we will confirm the appropriate method before the pour.
Who makes the test cubes?
Hixtra can sample and make cubes on site to the specified method, with initial curing arranged before the cubes are transferred for further curing and testing.
Can you core existing concrete to check strength?
Yes. Diamond core drilling can recover samples for laboratory testing. Tell us the location, dimensions, access and any services that need checking before drilling.
How much notice do you need for a pour?
Same-day and next-day testing dates are available in many areas. The earlier we know the pour date, sampling frequency and testing ages, the more easily we can plan the visit.
Do the results carry UKAS accreditation?
Where a method sits within our accredited schedule the report will say so. Ask us to confirm the accreditation status of each test before booking.
How do you take a representative sample of fresh concrete on site?
A composite sample is taken as several increments spread through the discharge of the load, then remixed on a clean non-absorbent surface before any test begins. Sampling is usually carried out to BS EN 12350-1. Where the sample comes from matters, because the very start and the very end of a discharge are not representative. We agree the sampling point with you beforehand, whether that is at the truck or at the point of placement.
What does a slump result actually tell you?
Slump measures the consistence, or workability, of fresh concrete, not its strength. The cone is filled and compacted in layers, lifted, and the drop in height measured, usually to BS EN 12350-2, then compared with the consistence class or target value in your specification. A result outside tolerance normally points to water content, admixture dosage or the time since batching rather than the mix itself. A collapse or shear slump is not a valid result and the test is repeated on a fresh portion.
How many cubes do we need per pour?
The number comes from your specification rather than from a single national rule. Sampling rates are normally set by the project specification, or by the identity testing provisions in BS EN 206 and BS 8500, and are expressed as one sample per volume of concrete, per batch or per day's pour. Each sample usually yields at least two cubes for each test age, so a 7 and 28 day requirement doubles the count. Send us the specification and the pour volumes and we'll confirm the number.
What else can you test on fresh concrete besides consistence?
Air content, fresh density and concrete temperature are the usual additions to a consistence test. Air content is commonly measured by the pressure method in BS EN 12350-7 and matters where the concrete has a freeze-thaw exposure requirement. Fresh density, usually to BS EN 12350-6, gives a yield and compaction check. Concrete and ambient temperature are recorded where the specification or the weather makes them relevant, and all of these can be carried out on the same sample during one visit.
What happens if the concrete fails a test at the point of delivery?
We tell the site straight away, and the decision to accept or reject the load is yours. Our job is to test, record and report what the concrete did, not to accept or reject material on your behalf. The result, the time it was taken and the delivery ticket details all go into the record, including for a load that is sent back, so you and the supplier have the same account of what happened. Rejected loads are then a matter between you and the producer.
Does adding water to the load on site affect the test results?
Yes, and it changes the concrete as well as the result. Water added after batching raises the water/cement ratio, which reduces strength and durability, and UK specifications commonly treat concrete that has had water added on site as non-conforming. Any addition should be recorded on the delivery ticket. A slump taken afterwards describes the concrete as altered rather than as supplied, so tell the technician at the time and the record will show what actually went into the works.
What do we need to provide on site for curing the cubes?
Cubes need a level, secure place to stand where they are protected from sun, frost, vibration and site traffic, and covered so they cannot dry out. Most sites use a thermostatically controlled curing tank, though an insulated box can work on smaller pours where a steady temperature is achievable. The cubes stay in their moulds for an initial period, usually overnight, before being demoulded and moved to controlled curing in water at 20 ± 2 °C until their test age.
How are the cubes identified so results can be traced back to the pour?
Each specimen is given a unique reference that ties it to the sample it came from, the delivery ticket and the part of the structure it represents. We record the date and time of sampling, the mix reference, the ticket number, the pour location and the required test ages, and those references stay with the cubes through curing, testing and the report. If your pour records use their own element numbering, send us the format and we'll follow it.
Plan the full testing programme.
Share the concrete specification, site postcode, pour dates, sampling frequency and testing ages. We can connect the site work with the relevant laboratory concrete tests.

Keep reading
Related testing guides.
In our customers’ words
A reputation built
on the work we do.
Trustpilot 4.8 / 5 ↑Independent feedback from the people we work with.
“Punctual, friendly and professional.”Read the full review →
“Perfect service and explained everything step by step.”Read the full review →
“Excellent service! Incredibly professional. Thankyou”Read the full review →